Stage Two Planning Progressing

After a period of consultation with interested parties the BCI Scheme has lodged applications for a suite of consents to enable the construction of a new intake and settling pond at Barrhill, a seven kilometer pipeline in the Rakaia River bed, and the installation of a small hydro generation plant.  This primary infrastructure will deliver to two distribution lines, the Barrhill Line and the Chertsey Line.

The scheme will soon be working with land owners and potential irrigators to finalise the layout of the distribution network.  The aim is to begin construction in autumn 2014 if the consent process is complete and irrigator support sufficient.

Springburn Line Commissioned

Infrastructure on the new Springburn line has been commissioned making water available to a new group of irrigators in the Springburn area.  The majority of the network was installed in the autumn but pond completion was held up due to wet conditions.

Land Use Consent Granted

The BCI Scheme has been granted a land use consent by Environment Canterbury which allows water to be supplied to new irrigators provided that all properties supplied water by the scheme do not in aggregate exceed a nutrient cap.

The scheme has developed a nutrient management policy which allows it to assess information provided with an application for water to establish if the environmental performance of the intended use of the water meets the expectation of the scheme and will not lead to the scheme exceeding the consented nutrient cap.  If new users of the water meet the scheme’s expected environmental performance, and they comply with the scheme’s requirements around farm environment plans and audit processes, they have the ability to change land use without requiring an individual land use consent. The consent is granted for a term of five years and the position may change in the future.

The consent is available for viewing here – Land Use Consent CRC141388

 

Lake Coleridge Storage Available

The BCI Scheme is contracting stored water with irrigators for the 2013/14 irrigation season and beyond.  This process has been enabled through the variation to the Rakaia River Conservation Order achieved by TrustPower Limited and a subsequent commercial agreement with the power generator.  Irrigators are being asked to nominate a contracted volume of stored water by 30th May 2013 for the upcoming season.  Details of the terms and conditions are attached on the following link;  Coleridge Storage – Fact Sheet 3

2013 Prospectus Released

Today a Prospectus was registered by BCI Limited to allow new irrigators to invest in shares and get access to water.  The Prospectus and Investment Statement are available on the BCI Ltd page.  New investors need to be aware that Environment Canterbury are yet to approve new consent conditions, under a revised planning platform, to allow new irrigators to use the water secured by making an application under this Prospectus.